Well they have started the render work. Render will be two colours - Woodland Grey & Dune. It seems like they have completed the tiling, and hopefuly should get some shots over the weekend.
No comments:
Post a Comment
Newer Post
Older Post
Home
Subscribe to:
Post Comments (Atom)
Order of Events
07/02/2009 - Deposit on Land/Builder Selected
25/3/2009 - House Contract Signed
03/04/2009 - Complete colour selection
09/04/2009 - Building permit received
15/04/2009 - Balance of House Deposit Payed
15/04/2009 - Final House Drawings Signed Off
16/04/2009 - Unconditional Finance Approval for Construction Loan
20/04/2009 - Land Settlement
22/04/2009 - Day 1 site scrape
8/5/2009 - Slab poured
08/05/2009 - Slab invoice received
12/05/2009 - Frame started
22/05/2009 - Frame invoice received
19/06/2009 - Lock Up Invoice Received
19/06/2009 - Lock Up Invoice Received
02/07/2009 - Fixing Invoice Received
Followers
Blog Archive
▼
2009
(27)
►
August
(2)
▼
July
(5)
Day 93
Render..
Tiling has commenced.......
Day 84........
Day 73
►