Day 84........

The painting of the internals is well underway and they are doing a neat job. The bricks have now been cleaned, so the rendering can start soon. The tiles have beed delivered and are waiting to be layed. We have finalised the quote for the driveway and decking ( I should have become a chippie)
Facade minus render Garage doors have been installed. The garage door colour is surfmist.
Bathroom. Waiting for the benchtop!!
Lots of tiles.
Ensuite tiles - 600x300 porcelains (Ivory)
The rest od the tiling is 400 x400 in a mocha colour.
Wall colour is China White with the skirtings and the ceilings in Lexicon Quarter. The better half could not decide on feature wall colours or wall paper so she kept it basic.
Cleaned slimline bricks.