Day 56
Central heating installed
Right Elevation
Started on the slimline bricks on the facade.
Right Elevation
Cavity sliding units have been installed as well as wall insulation.
Plaster delivered.
No comments:
Post a Comment
Newer Post
Older Post
Home
Subscribe to:
Post Comments (Atom)
Order of Events
07/02/2009 - Deposit on Land/Builder Selected
25/3/2009 - House Contract Signed
03/04/2009 - Complete colour selection
09/04/2009 - Building permit received
15/04/2009 - Balance of House Deposit Payed
15/04/2009 - Final House Drawings Signed Off
16/04/2009 - Unconditional Finance Approval for Construction Loan
20/04/2009 - Land Settlement
22/04/2009 - Day 1 site scrape
8/5/2009 - Slab poured
08/05/2009 - Slab invoice received
12/05/2009 - Frame started
22/05/2009 - Frame invoice received
19/06/2009 - Lock Up Invoice Received
19/06/2009 - Lock Up Invoice Received
02/07/2009 - Fixing Invoice Received
Followers
Blog Archive
▼
2009
(27)
►
August
(2)
►
July
(5)
▼
June
(5)
Fixing has started.................
Locked Up
Day 56
Close to lockup...
Bricks........
►
May
(10)
►
April
(4)
►
March
(1)
About Me
JC Building Diary
View my complete profile
No comments:
Post a Comment