skip to main
|
skip to sidebar
The Western Front
The Western Front
Wednesday, May 27, 2009
Roof Complete
No comments:
Post a Comment
Newer Post
Older Post
Home
Subscribe to:
Post Comments (Atom)
Order of Events
07/02/2009 - Deposit on Land/Builder Selected
25/3/2009 - House Contract Signed
03/04/2009 - Complete colour selection
09/04/2009 - Building permit received
15/04/2009 - Balance of House Deposit Payed
15/04/2009 - Final House Drawings Signed Off
16/04/2009 - Unconditional Finance Approval for Construction Loan
20/04/2009 - Land Settlement
22/04/2009 - Day 1 site scrape
8/5/2009 - Slab poured
08/05/2009 - Slab invoice received
12/05/2009 - Frame started
22/05/2009 - Frame invoice received
19/06/2009 - Lock Up Invoice Received
19/06/2009 - Lock Up Invoice Received
02/07/2009 - Fixing Invoice Received
Followers
Blog Archive
▼
2009
(27)
►
August
(2)
►
July
(5)
►
June
(5)
▼
May
(10)
Bricks Delivered
Roof Complete
Day 35
Day 32
Enemies!!
Happy?
The Slab
Tit for Tat!!
Day 14
Day 12
►
April
(4)
►
March
(1)
About Me
JC Building Diary
View my complete profile
No comments:
Post a Comment